348 infrastructure project show cost overruns of Rs 3 lakh crore owing to delay


Devdiscourse News Desk | Newdelhi | Updated: 07-10-2018 11:01 IST | Created: 07-10-2018 10:32 IST
348 infrastructure project show cost overruns of Rs 3 lakh crore owing to delay
  • Country:
  • India

As many as 348 infrastructure projects, each worth Rs 150 crore or above, have shown cost overruns to the tune of over Rs 3 lakh crore owing to delays and other reasons, a report said.

The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs 150 crore and above.

"Total original cost of implementation of 1,351 projects was Rs 15,72,066.02 crore and their anticipated completion cost is likely to be Rs 18,72,201.51 crore, which reflects overall cost overruns of Rs 3,00,135.49 crore (19.09 per cent of original cost)," the ministry's latest report for May 2018 said.

Of these 1,351 projects, 348 reported cost overruns and 263-time escalation.

According to the report, the expenditure incurred on these projects until May 2018 is Rs 7,47,302.42 crore, which is 39.92 per cent of the anticipated cost of the projects

However, it said the number of delayed projects decreases to 191 if the delay is calculated on the basis of the latest schedule of completion.

For 650 projects, neither the year of commissioning nor the tentative gestation period has been reported. Out of 263 delayed projects, 66 projects have an overall delay in the range of 1 to 12 months, 50 projects (13-24 months), 71 projects (25-60 months) and 76 projects (61 months and above), it added.

The report attributes the time overrun to a host of issues, including delay in land acquisition, forest clearance, supply of equipment, fund constraint, Maoist incursion, legal cases and law and order situation.

The brief reasons for time overruns as reported by various project implementing agencies are a delay in land acquisition, delay in forest clearance, delay in supply of

equipment, fund constraints and geological surprises, among others.

It also observed that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are under-reported.

(With inputs from agencies.)