Devdiscourse
Development News Edition
Give Feedback
write for Us

PMAY (Urban): 21.97 Lakhs houses completed against sanctioned 40.65 Lakh houses

A press report published in The Times of India for PM Awas Yojana is misleading.


Government Press Release India
Updated: 23-03-2018 13:08 IST
PMAY (Urban): 21.97 Lakhs houses completed against sanctioned 40.65 Lakh houses

The total number of houses which have been completed is 5.2 lakhs. (Image credit: GOI)

A press report published in The Times of India on 22nd March 2018 under the heading "PM Awas Yojana: Only 8 percent target met under Urban housing scheme" is misleading. The figure of "8 percent target met "was derived by using only the 'houses completed data' which is an incorrect application of statistics.

The progress of Pradhan Mantri Awas Yojana (Urban) can be measured by the fact that as on date 40.65 lakh houses have been sanctioned out of which 18.47 lakh houses have been grounded while 3.5 lakh houses have been completed. Apart from this, out of those houses which remained incomplete till March 2014 and sanctioned under JNNURM, 1.7 lakh houses have been completed. Therefore, the total number of houses which have been completed is 5.2 lakhs.

Moreover, the number of houses sanctioned by the government in the last one year is 21.65 lakhs. The housing projects normally take between 18 to 24 months to complete its life cycle of construction and hence houses grounded for construction is the true indicator of the real and physical progress of the scheme done at ground level.

Of the houses grounded for construction, 55 percent are at ground level, 12 percent at the foundation and the rest are at various stages of completion. The actual pace of the scheme started from October 2016 and the construction activities commenced from 2017 onwards, after the partnership with stakeholders and tendering activities.

An enabling ecosystem for Affordable Housing (of which PMAY (U) is a significant part) involving grant of Infrastructure Status, simplification of FDI process, introduction of PPP models, introduction of new modern and innovative construction technologies, increasing the carpet area of houses eligible for interest subsidy under CLSS for MIG and increase in coverage of areas under PMAY (U), amongst others are all gearing towards giving the necessary thrust to the pace of implementation of the Scheme.

The GST rate was also reduced from 12 percent to 8 percent for the houses constructed or acquired under the CLSS vertical of PMAY-Urban covering EWS, LIG, MIG I and MIG II and has been in effect from January 25, 2018.

With these measures, PMAY(U)is moving in the right direction. Every Month, more than 3 lakh houses are being approved under PMAY(U) and have moved at a fast pace as compared to earlier schemes

  1. During the 7-year mission period of JNNURM,12.41 lakh dwelling units were sanctioned; whereas the number of sanctioned houses have already reached more than 3 times under PMAY(U) (40.65 lakh houses) in less than 3 years.
  2. The rate of completion of houses under PMAY(U) is approx 14,252 houses per month which was only 8,333 houses per month under the earlier scheme.
  3. In the earlier Interest subvention Schemes (ISHUP/RRY), only INR 22.50 Crore was released to 18,166 beneficiary loan accounts while under PMAY(U) beneficiaries are five times (91,694) and interest subsidy is over 82 times (INR1,859 Crore).

The centre has released INR 13,582 crore as assistance to the states/UTs under this scheme. A mechanism for ensuring continued funding to States/UTs has been formulated with the approval by the Union Government last month to set up a National Urban Housing Fund for INR 60,000 crores in the Ministry for raising Extra Budgetary Resources (EBR) in phases for the rapid implementation of PMAY (U).

(This is a reproduced press release from the government of India as it is. Devdiscourse bears no responsibility towards grammatical or factual errors that may have been presented in the report.)

COUNTRY : India

POST A COMMENT