Parliament informed about stalled infrastructures and highway projects


Devdiscourse News Desk | New Delhi | Updated: 13-12-2018 16:09 IST | Created: 13-12-2018 15:58 IST
Parliament informed about stalled infrastructures and highway projects
Other factors behind the delay of projects include road over bridges and under bridges issues with Railways, public agitation for additional facilities, arbitration /contractual disputes with contractors etc, he said.
  • Country:
  • India

As many as 435 infrastructures and highway projects are stuck across the country on account of various factors, including delay in land acquisition and regulatory clearances, Parliament was informed Thursday.

"Four hundred and thirty-five numbers of infrastructure and road projects are stuck and pending for completion and they are delayed mainly due to land acquisition, utility shifting, non availability of soil/aggregate, poor performance of contracts, environment/forest/ wildlife clearances," Minister of State for Road Transport and Highways Mansukh Lal Mandaviya told the Lok Sabha in a written reply.

Other factors behind the delay of projects include road over bridges and under bridges issues with Railways, public agitation for additional facilities, arbitration /contractual disputes with contractors etc, he said.

"These projects are likely to be completed by October 2020," the minister said.

(With inputs from agencies.)