Four projects of Steel Authority of India Ltd (SAIL) worth Rs 2,338 crore are facing delay due to reasons like delayed placement of orders and supply of materials/equipment, Parliament was informed on Monday.

However, there is no cost overrun in these projects, Union steel minister Jyotiraditya M Scindia said in a reply to Rajya Sabha.

As per the information provided by the minister, SAIL is executing a project of the modification in the washing circuit of CSW plant of Dalli mines at Rs 168 crore in Chhattisgarh and another project is installation of a new sinter plant with an investment of Rs 1,111 crore at its Bokaro Steel Plant in Jharkhand.

SAIL is also rebuilding coke oven battery -2 (COB-2) along with augmenting coke handling and gas handling facility with an investment of about Rs 434 crore at its Rourkela Steel Plant in Odisha and rebuilding COB-7 & 8 at Rs 625 crore at Bhilai Steel Plant in Chhattisgarh, he said.

''There is delay in projects...mainly on account of poor performance of contractors/ sub-contractors, poor mobilisation of resources by the contractors, delay in placement of orders and supply of materials/equipment, etc. However, there is no cost overrun,'' Schinda told the Upper House.