Systemic Failures Exposed in George Building Collapse Investigation; 34 Dead
Minister Simelane emphasized that this lack of transparency allowed the construction company to bypass rigorous evaluation processes, putting the safety of workers and future residents at serious risk.
- Country:
- South Africa
An independent forensic investigation into the tragic building collapse in George, Western Cape, has revealed significant systemic failures in both the construction process and the regulatory oversight mechanisms. The Neo Victoria project, which collapsed on May 6, 2024, claimed the lives of 34 individuals and left several others injured, with many survivors still undergoing treatment. The findings of the investigation, presented by Human Settlements Minister Thembi Simelane, uncovered a series of procedural lapses, mismanagement, and non-compliance with critical regulatory standards by both the National Home Builders Registration Council (NHBRC) and project personnel.
Key Findings from the Investigation
The investigation, initiated by the NHBRC, highlighted a series of significant failures that led to the disastrous incident. Among the key causes cited in the report are widespread mismanagement, inadequate oversight, and critical violations of construction safety protocols. The collapse, which resulted in loss of life and extensive injuries, exposed a deeply flawed regulatory environment and a failure at multiple levels of oversight.
Irregular Homebuilder Registration Process
The investigation found serious irregularities in the registration process of the construction company responsible for the project. The contractor misrepresented its capabilities during the registration, failing to disclose its intention to build a multi-storey structure. The NHBRC requires full transparency regarding a homebuilder’s intended scope of work and technical capacity. The omission of such critical details breached NHBRC policies, compromising the integrity of the registration and the subsequent certification of the project.
Minister Simelane emphasized that this lack of transparency allowed the construction company to bypass rigorous evaluation processes, putting the safety of workers and future residents at serious risk. “This omission alone undermined the entire regulatory framework,” Simelane said.
Issues with the Enrolment Certification Process
One of the most troubling aspects of the investigation was the discovery of serious flaws in the enrolment process. The NHBRC's records showed that the enrolment forms for the project were processed on July 11, 2023, despite construction beginning on June 19, 2023. The delay in the enrolment process was compounded by the fact that the construction firm was allowed to begin building a multi-storey structure without proper enrolment approval. Furthermore, the investigation revealed that the official responsible for processing the enrolment forms used another staff member’s credentials to authorize the project.
Simelane expressed her concerns over these procedural breaches, stating that the irregularities in the enrolment certification were a significant contributing factor to the eventual collapse of the building. “The lack of proper checks and balances in the NHBRC’s internal systems paved the way for unauthorized approval and ultimately led to this disaster,” she said.
Deficient Inspection and Oversight Model
The NHBRC’s inspection model was also found to be deeply flawed. The report pointed to several instances where inspections failed to adhere to required internal protocols. One particularly alarming finding was that the first inspection took place eight days after enrolment, exceeding the NHBRC's mandated five-day inspection window. More troubling still was the fact that some of the inspection reports documented units that had yet to be constructed, which indicated significant lapses in the inspection process.
Minister Simelane also highlighted that the NHBRC inspectors were not empowered to enforce compliance with safety regulations, allowing critical safety violations to go unaddressed. The lack of accountability in the inspection process was a key factor that contributed to the unsafe construction environment that led to the building’s eventual collapse.
Occupational Health and Safety Violations
The investigation uncovered a number of Occupational Health and Safety (OHS) violations during the construction of the building. The safety consultant responsible for the project had resigned, and no other safety protocols were implemented in the absence of a qualified safety officer. The report also highlighted the absence of clear OHS enforcement protocols within the NHBRC, leaving inspectors without the necessary authority to address safety breaches effectively.
Simelane stated that the failure to ensure safety compliance at all stages of the project was one of the most concerning aspects of the investigation. “There were multiple red flags regarding the safety of workers during the construction phase, but due to the lack of enforcement and oversight, these concerns went unaddressed,” she said.
Qualifications and Competency Concerns
Further compounding the situation, the investigation found that several personnel involved in critical roles during the construction, including engineers and quantity surveyors, lacked the required qualifications. This lack of competence contributed to the technical errors that occurred during the construction process, which ultimately led to the structural collapse.
The technical manager, who was responsible for overseeing the construction, was found to have had inadequate qualifications, and their credentials were not properly reassessed before the project was approved. This oversight significantly contributed to the failures in construction and ultimately to the collapse.
Issues with the Geotechnical Report
The geotechnical report provided by the construction team was found to be incomplete and lacking essential information required for proper foundation design. Key details such as trial pit locations, Dynamic Cone Penetrometer (DCP) test results, and geological maps were missing, making it impossible to assess the suitability of the foundation for the multi-storey structure. This omission was identified as a critical factor in the structural failure.
Municipality’s Role in Approving the Building Plans
Another critical issue uncovered during the investigation was the role of the George Municipality in approving the building plans. The municipality gave its approval for the project after construction had already begun, indicating a lack of effective oversight on the local level as well. This approval, given outside of proper procedures, contributed to the failure of regulatory checks that could have prevented the collapse.
Recommendations for Reform
In light of the findings, the investigation issued a set of comprehensive recommendations aimed at preventing similar incidents in the future. Key among these recommendations is the proposal to explicitly define the types of buildings that a homebuilder is certified to construct, ensuring that construction companies are not permitted to take on projects that exceed their technical capacity.
Additionally, the report calls for the establishment of a peer review team to independently assess high-risk projects, such as multi-storey buildings, to ensure that they are in compliance with all relevant regulations and safety standards. The investigation also recommends that NHBRC inspectors undergo a comprehensive competency skills audit, and that a more thorough due diligence process be implemented for evaluating information submitted during the registration phase.
Accountability for Officials
The report also called for accountability for those officials who were implicated in the failures leading to the collapse. Charges of dereliction of duty, misconduct, negligence, dishonesty, and misrepresentation are expected to be brought against the individuals involved. Minister Simelane stressed that the NHBRC would follow due process in holding these officials accountable for their actions.
“We are committed to ensuring that those responsible for this tragedy are held accountable, and that future projects will be subject to the highest standards of safety and regulatory compliance,” Simelane said.
In conclusion, the George building collapse has exposed significant flaws in the construction regulatory framework and oversight processes. The recommendations made in the report serve as a call to action for all stakeholders in the construction industry to address these systemic failures and prevent similar tragedies in the future.

