Improper planning led to delays in Polavaram multi-purpose project: Report
- Country:
- India
Finding fault with the Andhra Pradesh government for failing to enforce contract conditions, the Comptroller and Auditor General have said the possibility of completion of the Polavaram multi-purpose project on the Godavari by the target date of 2019 "appear improbable."
In its audit report on the Economic Sector for the year ended March 2017, tabled in the state Legislative Assembly Wednesday, the CAG noted that progress of execution of Polavaram project had been slow, mainly due to "improper planning, delays in the finalization of designs, land acquisition, rehabilitation, and resettlement."
"As a result, the possibility of completion of the project and achievement of intended objectives by the target date of 2019 appears improbable. Audit findings indicate that completion of the project by June 2019 is a huge risk," the CAG report said.
It also found fault with the state government for failing to enforce the contract conditions and allowing several concessions amounting to Rs 1,853 crore to the head works contractor.
"Yet, the progress (or works) was not in tandem with the scheduled completion time. Despite slow progress and delays attributable to the contractors, the (Water Resources) Department failed to levy liquidated damages on the contractors," it said.
The CAG also pointed out that only four percent of the 1,05,601 project displaced families were rehabilitated in the last 12 years while rehabilitation and resettlement plans for 192 of 371 total villages were not even finalized.
It also said the AP government was yet to sort out submergence issues with neighboring states Odisha and Chhattisgarh and the construction of protective embankments to prevent submergence in those states had not yet commenced.
Importantly, the CAG noted, the AP government did not conclude a memorandum of understanding with the Union government as per the national project guidelines though more than four years have elapsed since Polavaram was declared a national project.
The state government, though, replied to CAG that a draft MoU was submitted to the Centre.
The CAG, however, said the state government should expedite the conclusion of the MoU with the Union Ministry of Water Resources so as to streamline the process of getting central assistance in a timely manner.
It also asked the state water resources department to improve its ability to enforce the contract conditions in the execution of project works to"avoid any further time overrun and cost overrun."
(This story has not been edited by Devdiscourse staff and is auto-generated from a syndicated feed.)
ALSO READ
Aarti Industries Strengthens Global Supply Chain with High-Value Contracts
Wisconsin Judge Convicted: Immigration Enforcement Showdown in Court
Wisconsin Judge Convicted for Aiding Migrant Escape: A Legal Battle Over Immigration Enforcement
Empathy Over Enforcement: India’s Approach to Overseas Deportations
Fribourg Canton Enforces School Mobile Phone Ban